- Rebuilt Lytton health centre may not be finished until 2028
Rebuilt Lytton health centre may not be finished until 2028
Early planning work is expected to conclude this winter, but construction and sign-off from province may take years
A new temporary health centre is nearly complete just north of the village of Lytton đˇ Interior Health
Former residents arenât the only people thinking about building anew in Lytton.
Two years after the village burned, and despite the grinding delays in rebuilding, local officials say they are fielding calls from outsiders or former residents interested in buying property in the community.
Meanwhile, a plan to rebuild Lyttonâs health centre could be completed this fall, but it still may take another five years for the facility to actually be built and open.
In April, The Current reported on the lack of plans to return critical health services to the ravaged town. Last week, residents received new information about when a new health centre will be built in townâand when actual rebuilding work in the village may finally begin.
Before it burned in 2021, St. Bartholomewâs Health Centre provided a broad array of services to residents of the village and a wide surrounding area. And while the blaze was two years ago, health officials have only recently started considering howâand in what formâthe facility will be rebuilt. Since the destruction of the village, residents have called for all the facilityâs old services to be returned, while warning that delays and uncertainty are causing current and former locals to reconsider their plans to return.
Lytton residents can now access some health services nearby in a Lytton First Nations health building to the north that escaped the brunt of the blaze. A temporary modular facility with more room, more services, and improved technology is expected to be opened at the same location in the next couple months.
But the old St. Bartâs site was located in the centre of a bustling village and included many other services, including an urgent care centre, pharmacy, lab, and even assisted living housing. And most of those services remain in flux or gone.
Interior Health doesnât have a plan yet to replace the facility, but in recent months it has finally begun work that will inform whatever is built next.
And residents have been clear about what they want to see, said Kathy Doull, the agencyâs executive director for the western part of the health region.
âWhat we heard is a very strong desire to have the previous services returned to the levels that were available before the fire,â she told an online community meeting held last week.
Residents emphasized the need for an on-site pharmacy, a place to get lab tests taken, and a facility that can provide urgent care treatment, especially for non-life-threatening ailments like cuts, sprains and burns. Doull said that the new facility will be planned using that feedback.
âAll of those things that we heard, those are the things that weâre taking into account when weâre designing and delivering services.â
But there are some new hurdles, she warned.
The old centre had six assisted-living beds for seniors. But since that facility was built just 15 years ago, the province has created new standards that donât permit the construction of such small assisted living sites, Doull said.
That doesnât mean assisted living is impossible, she added.
âWe have to look at what is needed in the community, we have to look at what is feasible, and we have to maybe look at how we can be creative,â she said. âMaybe itâs assisted living mixed with something else so we can meet the guidelines and staffing levels that are required.â
Doull noted that residents have asked for other forms of seniors care in a new facility, including palliative care housing.
If the receptiveness of Interior Health to provideing a similar level of health service is the good news, the bad news is just how long it may take.
Doull said officials hope to have a concept and business plan ready for the Ministry of Health by this fall. Design could take place over the winter, she said, with construction beginning next summer.
But Doull said it will likely take three to five years for the facility to actually be constructed. And that timeline is itself uncertainâand only partially in the hands of Interior Health: Doull noted that provincial officials must sign off on theh project before any ground is broken.
The track record of Lyttonâs rebuilding so far, and the various factors that have slowed it downâfrom archeology work to bureaucracy to weather eventsâprovide reason for skepticism.
Still, some clarity seems to be coming.
When asked by Tricia Thorpe, an elected representative for rural residents in the area, about when residents will know enough about the future health centre to start making plans for their lives, Doull said: âthat should be coming quite soon. By the end of this year, we should have defined what that future state looks like so hopefully that question will be answered and people will be able to make firm decisions.â
â----
Meanwhile, work to allow property owners to start rebuilding this summer or fall continues to sputter. Contaminated soil remains piled on many streets around town, growing weeds. And while it had been hoped that the backfilling of sites with clean soil was to be well underway by now, that has been delayed for weeks because of ongoing discussions about archeological work.
The villageâs new recovery manager, Mike Blaschuk, said he expects that work to resume soon. Only last week did officials finally receive permission to start removing the contaminated soil piled around town. Blaschuk expected that work to start Monday. One local reported Tuesday that removal of the piles was underway.
Work hasnât been completely stalled, Blaschuk saidâthere are other issues that have been addressed in the meantime. A test backfilling project was used to set the stage for work throughout the first neighbourhood to be prepared for redevelopment.
And so the rebuild drags on, without much rebuilding yet. But whenever the health centre is complete, it seems possible that it will serve a community with plenty of energy.
Blaschuk said there is plenty of interest from those hoping to live or build in the new Lytton.
âWeâre getting regular calls from people looking for lots,â Blaschuk said. Some of those people lived in the area, while others are selling property elsewhere and are interested in building a new home in the village. But, he noted, there are no lots currently for sale.
Blaschuk, a former vice-president of BC Housing, said he has also been talking to the agency about potential affordable housing projects in the village. And discussions with owners of commercial properties may lead to new mixed-use buildings, with housing giving a boost to retail and business developments that may not otherwise be financially feasible to rebuild.
That, plus a provincewide demand for housing, suggests a rebuilt Lytton could end up being just as vibrant and busyâif not moreâas the tiny bustling village that burned in 2021.
If you read and appreciate our stories, we need you to become a paying member to help us keep producing great journalism.
Our readers' support means tens of thousands of locals in the Fraser Valley can continue getting local news, and in-depth, award-winning reporting. We can't do it without you. Whether you give monthly or annually, your help will power our local reporting for years to come. With enough support, weâll be able to hire more journalists and produce even more great stories about your community.
But we arenât there yet. Support us for as low at $1.62 per week, and rest assured youâre doing your part to help inform your community.
Join us, make a difference, and become a Fraser Valley Insider member today.
- Tyler, Joti, and Grace.
Reply