The provincial government has finally conceded that even the first stage of widening Highway 1 to Abbotsford will take years longer than promised.

The province issued a press release Tuesday declaring that work had begun to clear the median between 264 Street in Langley and Mt. Lehman Road in Abbotsford. And included in the release was a new completion date for the stretch of highway: 2029.

There is still no official date for the completion of work further east, where the province says construction will be further delayed in order to minimize traffic disruptions.

The province had originally promised to widen Highway 1 to Abbotsford by 2026.

But in August, Dan Coulter, the Chilliwack MLA who is also the Minister of State for Transportation and Infrastructure, told The Current that work through to Sumas Way won’t be completed until the mid-2030s. The declaration triggered a follow-up declaration from ministry staff that Coulter “misspoke” and that a timeline hadn’t been set.

The 2029 completion date revealed Tuesday suggests Coulter may have not been far off the mark.

That timeline applies to the Phase 3A stretch of the ongoing highway widening project. The province says work to clear the median on the Phase 3B stretch between Mt. Lehman Road and Sumas Way could begin next year. But the ministry has also said that in order to reduce the scale of traffic disruptions, actual construction on Phase 3B will wait until the bulk of 3A work is completed.

The Phase 3B work includes an incredibly complex interchange—at Sumas Way/Highway 11—along with additional work at the McCallum and Clearbrook junctions. That will inevitably force construction to stretch well into the 2030s.

The province has blamed the atmospheric river for the delays, though flooding from 2021 didn’t impact any portion of the highway west of the Sumas Way interchange.

Subsequent widening work across Sumas Prairie, between the Highway 11 interchange and No. 3 road in western Chilliwack, is being re-imagined in the wake of the 2021 flood. The province says it will spend $30 million on an “integrated planning study.”

Billion-dollar project

The province has also revealed the budget for the next stage of work.

It says widening the highway between 264 Street and Mt. Lehman Road is expected to cost $2.3 billion.

The largest single project in the stretch of road will be the rebuilding of the 264 Street interchange. Construction on that junction is expected to begin next year.

Elsewhere, the new highway is expected to include dedicated bus lanes, an HOV lane, and cycling and a pedestrian path. You can see those details here.

Reply

Avatar

or to participate

Avatar

Greg McKone3 years ago

It always drives me crazy how these projects get stretched out... As if the construction companies are guaranteeing long term employment for their staff rather than trying to deliver value to citizens as early as possible.

I've been hoping (and repeatedly disappointed) to see a reluctance to deliver value early. e.g. Rather than focussing on the shortest stretch on a single side and providing a working lane before moving on to other parts, there seems to be a "little here, little there" approach that delays value till the very end.

Pick a direction (East / West) Pick the shortest link and finish that, then continue in that same direction, linking pieces together till the entire East/West bound work is complete.

(at the same time the other side shouldn't be slowed or interrupted). Then switch sides, put all the effort into the other side and complete that.

The citizens get benefit sooner on the first side and can enjoy that the entire time the 2nd side is in progress.

Avatar

John Conner3 years ago

Extremely long period of time to build, I commute to Vancouver many times a week and pass the highway work - many of those days only a few workers are on site. There is night work however a number of trucks and equipment and not a lot appears to be done. Maybe the contractor is short staffed or the treasury is stretching out the project to pay only minimum amount. We are not told the details. Good thing I will be retired in 10 years. Oh wait, may be half done by then!

Avatar

Paulus Vrijmoed3 years ago

They were able to complete the Coquihalla hwy in about two years in time for Expo 86. How could they not complete a relatively short stretch of hwy in a matter of a year, maybe two?

Avatar

Sharon Edwards3 years ago

Gas taxes used to be used for highway and bridge building!!!!

Avatar

Rob Bowden-Green3 years ago

We need competent politicians that can get things done in 4 years and ignore all the Political BS....If they can't do the job vote them out.

Avatar

Rob Murray3 years ago

Welcome to Supernatural British Columbia land of the highways that time forgot. We’re building tomorrow the highway you needed yesterday. Maybe.

Avatar

Brad Faucher3 years ago

I’d like to know how did we build so many highways in the 50’s and like one person said the coquihalla in 20 months but it will take a decade to add a couple lanes to the highway 1! Bull doze some dirt and add some dirt with black top and let’s get at it government!

Avatar

John Viggiani3 years ago

Well...this entire Hwy 1 project is about 50 to 60 years behind schedule already (when compared to other projects in Canada). And how did he Coquihalla Hwy get built in 20 months? So it isn't a surprise that when all is said and done all the way to Chilliwack, it will likely be 2050!

Avatar

Frank Bucholtz3 years ago

The widening project is complex, but there have been a huge number of delays that are the direct responsibility of the provincial government. It is doubtful that this announcement, and the small amount of work which will commence soon, would even be happening if there wasn’t a provincial election next year.

Avatar

Karen Skjonhals3 years ago

Come on DDP you can do better. The traffic is so congested now, taking so long isn't going to work. Make this a priority and get the job done.

Avatar

Lorne Smith3 years ago

Most of this section of highway hasn’t been upgraded since it was built 60 years ago. The inactivity is inexcusable.

Avatar

John Viggiani3 years ago

Thank you Tyler for investigating. It is such a frustrating thing about how slow our government is about important issues. And yes (to another comment), compared to some other provinces or countries our highway infrastructure Is pretty pathetic. I am thankful i do not need to commute for my job.

Avatar

Richard Stafford 3 years ago

Would have been done already if we hadn’t elected NDP same as Massey tunnel

Avatar

Gerald Timmerman 3 years ago

Iam on this highway every day ! Nothing absolutely nothing is happening on this highway construction,it is a joke Maybe have a look in Europe and its infrastructure ,stuff gets done over there ! If this continues the economy will suffer big time!

Avatar

Seanna Koopmans3 years ago

It would go faster if they actually worked on it. I don’t travel Hwy 1 more than a couple of days per week but when I do go through at 8:00am & 5:30pm I almost never see anyone working. And it’s never more than a handful. How about a few extra shifts to make it go faster?

Avatar

R Mer3 years ago

Can't spend $30 million on "planning" and actually have shovels in the ground.......... might interfere with the planning process.